Says all infra projects to be completed within stipulated time frame
BUDGAM: The Deputy Commissioner (DC), Budgam, Akshay Labroo today conducted site inspection of construction of Transit Accommodation for Kashmiri Migrant employees at Kakenmaran and PRI members’ Accommodation at Sheikhpora and inspected ongoing progress of these projects.
While inspecting the ongoing process at different blocks, the DC said that work on 10 out of 12 blocks comprising 194 flats at Transit Accommodation, Kakenmaran is going on in full swing.
He instructed concerned to expedite work process on blocks to ensure the project is completed within the stipulated time frame.
Later, DC also inspected progress of ongoing PRIs Accommodation project at Sheikhpora and inspected interior works in different flats.
DC said that the project is nearing completion and soon shall be dedicated to the concerned to strengthen the democracy at the grass roots level.
The DC directed concerned to expedite pace of work and complete construction of pending boundary wall construction, lawn and pathway development and approach road.
He said that the District Administration is keen on completing all infrastructural projects within the deadline so that the same are dedicated to the general public at the earliest.
Similarly, review of Clock Tower, multi story car parking and beautification works in Budgam are also being given special focus by the district administration.
Among others, ADDC Dr Akramullah Tak, JD Planning, ACD, ACP, Executive Engineer R&B, Tehsildar, BDO and other officers also accompanied DC during inspection of projects.